I want to update the Unit Rate for Existing Project Templates.
Update done to screen ID pm208000, Project Template
Only require update to the Revenue Budget Tab
The result is that the Project template is updated with the Revenue budget Project task, but a new Inventory ID is created with the new rate. Hence, I am unable to update the Project Task and Inventory ID combination
Example of import scenario.
Error on import:
Violation of PRIMARY KEY constraint 'PMBudget_PK'. Cannot insert duplicate key in object 'dbo.PMBudget'.
Any suggestions?
The following worked for me.
Here's the Data Source in Excel:
Here's the setup of the Import Scenario:
Here's what the Project Templates (PM208000) screen looked like BEFORE running the Import Scenario:
And here's what the Project Templates (PM208000) screen looked like AFTER running the Import Scenario: